Skip to content

A miswired panel causes a fire. What pays for the fire, and what pays for the rewiring?

By , CEO, Rayon · Last reviewed

Builder’s risk pays for the fire damage that follows. The cost of correcting the defective work itself is excluded. How much is carved out depends on which defects clause the policy carries: LEG 2/96 excludes what it would have cost to fix the defect before the damage happened, while LEG 3/06 excludes only the cost of improving the original work.

Want this checked on your own certificates? Bring 50 you have already sent and keep the findings. Book a walkthrough

What is the difference between the damage and the defect?

Property policies for construction separate two things: the faulty part, and what the faulty part destroys. A miswired control panel is the defect. The fire in the hall is the resulting damage. Builder’s risk is written to pay the second and not the first [2]. The LEG clauses are model defects wordings from the London Engineering Group, and under both a part of the insured property is not regarded as damaged solely because it contains a defect [1]. Where a defect causes no physical damage at all, see who pays when a commissioning test fails and nothing is damaged.

How do LEG 2/96 and LEG 3/06 differ?

ClauseWhat it leaves outEffect for the contractor
LEG 2/96The cost that would have been incurred to put the defect right immediately before the damage occurredThe rewiring cost comes out of the claim
LEG 3/06Only the cost of improving the original design, materials or workmanshipMore of the repair is paid, including damage to the defective part itself

Why does a subcontractor care, if the owner buys builder’s risk?

  • The owner or general contractor chooses the clause, and you inherit it.
  • Whatever the builder’s risk policy does not pay is likely to be claimed from the trade whose work was defective.
  • Your own general liability policy excludes damage to your own work [3], so the rework usually lands on your balance sheet. The exception for work done by your subcontractors is in what the “your work” exclusion means when you sub out scope.
  • The deductible on a data-center builder’s risk policy can be larger than a small subcontract’s margin, and contracts often pass it down.

What should I ask before signing?

Sources

  1. Carter Newell, Judicial consideration of LEG 2 and LEG 3
  2. AGC, Insurance Issues in Constructing Data Centers: A GC’s Perspective (2026)
  3. ISO CG 00 01 04 13, Commercial General Liability Coverage Form

How these articles are written and checked. General information, not legal advice or an interpretation of your policy. Policy forms and endorsements control. Form numbers are © Insurance Services Office, Inc. and are cited for reference.